Skip to main content.

Multiple perspectives for a highway project

Purpose

An urban road authority planned to extend its arterial road network with a major toll road. It chose a build, own, operate and transfer (BOOT) strategy for procurement, and it had gone to tender to select a consortium to undertake the work.

The main construction contractor in a leading joint venture (JV) wanted to identify the risks it faced in its own activities to improve the quality of its tender. It also wanted to understand how the road authority might perceive the risks, to enable it to take the authority’s views into account in its submission and adopt a proactive approach to managing the authority’s concerns.

Project context

The project involved the design, construction and operation of a new toll road, to connect an existing highway with another recently constructed high-capacity road. It would form an important link in the urban arterial road network, for both commuters and industrial users. It was intended to reduce traffic congestion, travel time, accidents and fuel use on the existing highway network, accommodate continuing traffic growth and reduce adverse impacts of through traffic on residential roads.

Underground construction, including two bored tunnels, a cut-and-cover tunnel and ventilation shafts, formed an important part of the project.

The JV consisted of a major construction contractor, a road maintenance provider, a provider of tolling services and a consortium of banks.

The primary stakeholder as far as the JV was concerned was the road authority that would award the toll road concession. Other stakeholders included:

  • Commercial land users and developers
  • Community groups
  • Contractors and sub-contractors
  • Emergency services
  • Local authorities
  • Local Members of Parliament
  • Ministers and Government departments
  • Residents adjoining the road corridor
  • Road users
  • State taxpayers.

Approach

Overview

The international standard ISO 31000 Risk management – Principles and guidance (Figure 1) provided the framework for the process. Two risk assessments were undertaken, the first from the perspective of the JV and the second from the perspective of the road authority. The road authority was not involved in the exercise: the JV conducted both assessments, putting on a ‘road authority hat’ for the second one.

Figure 1: Risk management process, ISO 31000

Criteria

Stakeholder objectives were reviewed and condensed to sets of criteria for the project, one set for the contractor (Table 1) and one for the road authority (Table 2).

Table 1: Success criteria for the contractor

Criterion

Notes

Cost

Construction and operating budgets met, whole-of-life cost minimised, profit maximised, operations and maintenance costs kept low

Environment

Environmental aspirations of the community met in construction and operations, legislative compliance satisfied, visual impact minimised

Goodwill

Impact of traffic on the local community reduced, adverse impacts of through traffic and construction traffic on residential roads reduced, good community relations maintained

Quality

Traffic efficiency improved, congestion reduced, travel time reduced, fewer accidents, lower fuel use, scope to accommodate continuing traffic growth, high quality building and maintenance

Reputation

The contractor’s presence and reputation established in the underground construction market

Safety

Safe job, no lost time injuries

Schedule

Construction milestones met

Table 2: Success criteria for the road authority

Criterion

Notes

Cost

Costs to Government minimised

Probity

High standards of probity observed in the tendering process

Quality

Project built and maintained to high quality standards

Schedule

Delivery milestones met

Tolls

Minimise tolls, particularly in the early years of the concession

Key elements

Key elements are used for structuring the assessment activities. The elements selected in this instance are summarised in Table 3 for the contractor C and in Table 4 for the road authority R.

Table 3: Key elements for the contractor

Number

Element

C1

Preliminaries

C2

Road works

C3

Bridges and structures

C4

Driven tunnel

C5

Cut-and-cover tunnel

C6

Electrical and mechanical

C7

Service diversions

C8

Operations and maintenance

C9

Relationship with the authority

C10

Community relationships

Table 4: Key elements for the road authority

Number

Element

R1

JV capability

R2

Construction

R3

Operations and maintenance

R4

Community issues

Workshop participants

The main construction contactor in the JV consortium initiated the workshop. Workshop participants were senior members of the JV project team, senior members of the constructor who were involved in similar projects elsewhere, senior members of the consortium having recent dealings with the road authority and selected specialist advisers. (The road authority itself could not be involved for probity reasons.)

Workshop outcomes

JV perspective

Figure 2 shows the risk profile for the JV. There are some extreme risks associated with the driven tunnel and the JV’s relationship with the road authority.

There are a few major risks associated with road works, bridges and structures, service diversions, operations and maintenance, community issues and other issues. The contractor and other JV members felt they had the experience and ability to manage most of these well, and few of them were urgent at this early stage in the tendering process.

The risks with agreed ratings of extreme or major all required management attention at a senior level. The JV Project Director undertook to allocate responsibilities after the workshop and develop treatment plans as appropriate for these risks.

Figure 2: Risks for the JV

Road authority perspective

Figure 3 shows the risk profile for the authority, as perceived by the JV. The greatest concerns for the authority were assessed as the capability of the JV and community issues. The implication for the JV was that it must address these issues explicitly in its submission. Two areas that required special attention were:

  • The ability of the JV to demonstrate its tunnelling experience in local conditions, and particularly for the driven tunnel
  • The capabilities of the specialist contractors and sub-contractors to be used for electrical and mechanical works, particularly in the underground portions of the road.

Figure 3: JV’s view of risks for the authority

The tender was designed to address these concerns directly and provide evidence that would demonstrate that the road authority could have confidence in this JV and its proposal.

Outcome of the tender

The JV’s tender was successful, as was the project.

Lessons

When preparing a tender response, considering the point of view of the entity that has called for tenders can be very valuable, particularly if the evaluation of responses will involve many criteria and trade-offs. For a tenderer, taking a different viewpoint provides insights into the concerns of the project owner that help to develop a better tender response. If the owner’s evaluation team can see clearly that their key issues have been recognised and addressed then they are more likely to be disposed favourably towards the tenderer.

However, taking a different view requires more than simply thinking about what the other party might feel. It requires a deliberate effort to enable personnel to put themselves in the place of the other party.

  • Structurally, the criteria and key elements used in the analysis must be adjusted to suit each perspective and focus attention on the key areas of concern of each of the parties, as they were here.
  • The participants in the assessment must consciously adopt another perspective, something that is not easy to do in practice. The facilitator, preferably someone independent of all parties in the tendering process, needs to remind them regularly of the role they are taking and the way they need to look at the world. This is best done in a separate workshop, as was the case here, and preferably off-site, away from the office and in different physical surroundings.
  • Where possible, participants who have worked with and understand the project owner before should be involved in the assessment.